When designing and building tooling for a new GM project, Pentar made recommendations to our customer suggesting a redesign of the part, which would dramatically reduce the assembly cost. This could not be accomplished in time for validation or PPAP for launch, however, the change was made in the second year, saving $180K over the balance of the seven-year program.